A padel court can usually fit into the area of a tennis court (approx. 36.6 × 18.3 m) without an extension. If the area is widened to around 21 m, up to three spaces across are possible. In Switzerland, conversion usually requires a building permit, and there are no fixed limits for sports noise: the authorities decide on a case-by-case basis.
- Capacity: one space on the existing area, up to three with widening to approx. 21 m.
- Permit: Building application submitted of the municipality, procedure depending on the canton.
- Noise: LSV without fixed limit values, individual case assessment, padel is around 5 dB louder when hitting the ball.
- Duration: approx. 3 to 6 months, pure construction time 4 to 8 Weeks.
- Tip: Talk to the building authority early, before you order.
How many padel courts fit on a tennis court?
A padel court measures 10 × 20 meters (internal dimensions according to FIP), the total area of a tennis court is around 36.6 × 18.3 meters.
- Without Extension: The square is 20 m long and the area is only 18 m wide. A padel court usually fits without any problems.
- With widening to approx. 21 m: Three courts can be arranged side by side.
- Several tennis courts: often offer more scope.
Example: three padel courts across a tennis surface widened to 36.6 × 21 m. Each system must be measured on site.
Is the tennis court suitable as a substructure?
- Sand court (brick dust): is usually not directly suitable, as a rule a new concrete slab is required.
- Hard court: can serve as a base depending on its condition, thickness and evenness, which saves money Costs.
- Drainage: Outdoors, the space needs a slight slope and a functioning drain.
Does it need a building permit?
As a rule, yes. Glass walls, steel structure and lighting are a structural change. The building application goes to the municipality, each canton regulates the procedure in its own planning and building law.
| What is checked | What it is about |
|---|---|
| Zone conformity | Is sport allowed in this zone? |
| Noise | How bad are the neighbors affected? |
| Light | Are the headlights blinding? |
| Limit distances and height | Glass walls and roofing |
The building application is usually made public. Neighbors can raise objections during the objection period.
Noise protection: the most important point
Measurements by an acoustic software manufacturer showed that the ball hit values were around 5 dB higher than in tennis, plus there are glass walls and four players. The Noise Protection Ordinance (LSV) does not contain any fixed exposure limits for sports facilities; the authorities make judgments on a case-by-case basis based on the FOEN enforcement aid “Noise from sports facilities”. The closer residential buildings are, the sooner an appraisal is required.
- Location and orientation with the greatest possible distance from residential areas.
- Roofing or hall significantly reduces the noise from the outside.
- Noise barriers or sound-absorbing elements.
- Operating times and community quiet times.
- Inform neighbors early.
This article is an overview and not legal advice. The responsible authority is decisive. Discuss your project with the building authority early on.
How much does the conversion cost?
There are hardly any public price comparisons for Switzerland. For guidance, a German specialist retailer gives these guideline values for 2026 (net, in euros):
| Position | Reference value Germany 2026 |
|---|---|
| Complete open-air space | approx. € 60,000 to 100,000 |
| of which foundation and earthworks | approx. € 20,000 to 35,000 |
| of which LED lighting | approx. € 1,800 to 8,000 |
| Space on a stable hall floor | approx. € 17,000 to 34,000 |
In Switzerland the costs may vary due to wages and fees. If you build several places together, you usually pay less per place. You will only receive a binding number with an offer for your location. How this works out is stated in “How much does a padel court earn?”.
Procedure in 6 steps
Preliminary clarification
Zone, noise, light and procedures with the municipality clarify.
Planning
Number of places, model, lighting, possibly roofing.
Building application
Submit documents, condition, objection period.
Production
The places are made to measure, possible parallel to the process.
Construction and Assembly
Adjust the foundation, install the space, approx. 4 to 8 weeks.
Opening
Booking system, courses and opening event.
Checklist for your board
- Measure the area, including paths, fences and masts
- Check the surface and substructure let
- Check the distance to residential buildings and the zoning plan
- Preliminary discussion with the building authority
- Decision on open air or roofing
- Obtain an offer and clarify financing
- Inform neighbors
- Plan booking and access, for example via Club automation
Frequent Questions
How many padel courts fit on a tennis court?
One padel court usually fits on the existing area. If it is widened to approx. 21 m, up to three courts across are possible.
Does a padel court in Switzerland need a building permit?
As a rule, yes. The building application is submitted to the municipality, and each canton regulates the process itself.
Are there noise limits for padel courts in Switzerland?
The LSV does not contain any fixed noise limits for sports facilities. The authorities assess sports noise on a case-by-case basis, based on the FOEN enforcement assistance.
Is padel louder than tennis?
Yes. Measurements showed that the ball hit values were around 5 dB higher. There are also glass walls and four players per court.
Can the tennis surface serve as a substructure?
A sand court usually needs a new concrete slab. Depending on the condition, a hard court can serve as a basis.
How long does the renovation take?
As a guideline, 3 to 6 months from planning to opening. The actual construction time is approx. 4 to 8 weeks.
Are you planning a renovation?
We accompany Swiss tennis clubs from the preliminary clarification to the opening.
More about padel court construction Advice via WhatsAppThis might also interest you
- Building a padel court in Switzerland: The guide for clubs, communities and hotels
- How much does a padel court in Switzerland earn? The invoice in CHF
- The padel club that runs itself: automation with Playtomic, access and light
Accessed in November 2026. Tips and assessments are also based on our experience as players, trainers and specialist retailers.
- FIP: Rules of the game padel (PDF). Padel:
- BAFU: Enforcement assistance noise from sports facilities (PDF)
- Canton of Schwyz: Sports noise
- DataKustik: Padel noise
- Everything for padel: Costs and Conversion, guideline values Germany

















